Park Shore Beach Project Reaches Halfway Mark

By Pam Nicholls, GSAC Board Member Submit questions or feedback online  The Park Shore Beach Renourishment project entered its sixth week on February 24th and is over the halfway point when it comes to sand placement with 172,150.02 tons delivered in about 8200 truck loads. Project Manager Larry Humphries confirmed the project had reached 1000ft north of [...]

By |2025-02-27T14:46:24+00:00February 27th, 2025|News|0 Comments

Park Shore Beach Project Underway Despite “Angry Seas”

By Pam Nicholls, GSAC Board Member Submit questions or feedback online  Collier County’s Park Shore Beach Re-nourishment project started on schedule on January 6, 2025. Two weeks in, approximately 45,000 tons of sand has been delivered to the northern section of the project. Project manager Larry Humphries told the newsletter that “angry seas” had prevented the [...]

By |2025-01-22T16:03:05+00:00January 22nd, 2025|News|0 Comments